|
Trilore's
ME process gives cast part users unprecedented flexibility. Trilore can provide parts in virtually any hypo-eutectic
aluminum alloy, can provide these with dimensional accuracies
beyond the standard RPM process, with tooling that can be
expanded almost overnight to meet you volume needs.
The ability to cast in
different aluminum alloys means not having to compromise
between mechanical properties, thermal conductivity or alloy
compatibility.
Tighter tolerances means
significantly less machining of parts; indeed, in many cases
machining is eliminated, reducing the costs of secondary
operations. See
tolerance
page for details on tolerance control provided by ME.
Rapid response
tooling means when your quantity needs increase, Trilore can
meet those increases with ease.
Comparisons of Die-Castings and castings made with
Trilore's ME process
Trilore's ME process was developed to
meet a need in the die cast prototype market for a process
that provided analogous parts for testing prior to the release
of data for production die casting. The most important
attributes identified as we developed the ME process were:
After 2 years of development, the ME
process achieves the best mix of these attributes. Below is a
summary of the expectation a customer can have for ME castings
for each attribute when casting with die cast alloys:
Mechanical Properties
It is understood that if one specific
alloy is used in different casting processes, conventional
thermodynamics says that the only way to change mechanical
properties is to change the rate of cooling of the alloy. This
might occur during the casting process, or in a subsequent
heat-treat process after the cast process. There are some
additional methods now available such as the HIP process or
the addition of grain site promoters, but typically the rate
of cooling of a part determines mechanical properties. In the
simplest terms, faster cooling means smaller grain structure,
and smaller grain structure means better mechanical
properties.
If you look at the rate of cooling
between the different casting processes, the die casting
process appears to provide the best overall mechanical
properties at a cooling rate to solidification of 10 to 12
Degrees C/second. A higher cooling rate will create depleted
silicon zones that reduce mechanical properties. Lower cooling
rates may cause low density (porosity). Other casting
processes have different cooling rates. Typical rates for
various section thicknesses are as follows:
Die Casting : 12 - 500 Degrees C/sec
ME Casting: .8 – 2.2 Degrees C/sec
Permanent Mold : .3 – 1 Degrees C/sec
Sand Casting: .1 - .5 Degrees C/sec
RPM: .05 - .2 Degrees C/sec
When the DCS (dendritic cell spacing)
of typical die castings and castings made with the ME process
were compared, the DCS of ME castings where about 4 times
greater than those of the die casting of comparable section
thickness. Please note the comparison was made at comparable
depths within the sections of the castings, and below the
chilled surface of the die-casting. This means that in the
as-cast condition, the mechanical properties of the ME casting
were significantly lower than those of the die-casting using
the same alloy. However, due to the lack of trapped air in the
ME casting, we have the capability of heat-treating the
casting to increase mechanical properties. Typical mechanical
properties of test bars poured along with the castings are as
follows for 380 alloy:
Die Casting (Book values)
ME Castings
Tensile Strength (ksi) 46
33
Yield Strength (ksi) 23
21 - 26
Elongation (%) 3.5
2.5 – 3.5
Dimensional Tolerances
Typical dimensional tolerances for ME
castings are as follows. (Please note these are to a nominal
tolerance based on the first part(s) poured, see Tolerance
page)
+/- .007 inches for the first 8
inches (+/- .18 mm to 200mm)
Add an additional .0005 inches per
inch for every inch over 8 inches (.012mm for every additional
25.4 mm)
Core and parting lines are + .010
inches, - 0.00 inches for the first 8 inches
These are typical of standard NADCA
allowances for die-castings with the exception of the core and
parting line dimensions. The ME molds are plaster molds that
are assembled by hand, so the parting lines created by
additional plaster pieces used to make features that are not
in die draw tend to be slightly less accurate than what can be
achieved in die castings but closer than what can be achieved
with any other casting process.
It should be noted that holes less
than 3/8 inch in diameter or any feature that is required to
be better than .015 inches to true position is machined into
ME castings to assure meeting dimensional requirements.
Surface Finish
The typical as-cast surface finish of
ME castings is 64 micro inches. The biggest difference between
a die-casting and the ME casting is the area around a core
pull feature. For example, an undercut feature on a
die-casting would have a core pull scar at the beginning of
the undercut (picture a hole with a core scar around the
diameter of the hole). The ME casting will have a core scar
stepped away from the undercut feature that also extends to
the parting line of the mold.
Lead Time
The standard lead time quoted for the
ME casting is 4-5 weeks for the first as-cast parts after
receipt of a finished casting database. The typical times for
the various processes in the tooling and casting process are
as follows:
Creation of a master pattern: 1-2
weeks
Creation of the tool used in the
foundry: 2 weeks
Time to make the initial castings 1
week
The timeline for the actual casting
process includes making the plaster mold (1 day), pouring the
metal into the mold (1 day), grinding the casting (1 day) and
finally the heat treat and final inspection of the part (2
days).
|